Jining Xinyao Machinery Co., Ltd., Tangshan Baofeng Pipe Pile Co., Ltd., Chengdu Hengruitai Construction Engineering Co., Ltd. Jining Xinyao Machinery Co., Ltd. was established in 2017 and deals and sells engineering machinery and accessories; electrical machinery, mining equipment and accessories, auto parts, plastic products, rubber products, standard parts, electrical equipment, steel, hardware products, office products. Sales of supplies. Power generation micro pile pile heads from Jining Xinyao Machinery Co., Ltd. are of the best quality and most cost effective. Chengdu Hengruitai Construction Engineering Co., Ltd. focuses on: hot spring geothermal well development; hydrogeological and geophysical studies; exploration and development of geothermal resources; and full use; development and use of geothermal resourcesues; new investments in geothermal energy; exploration, design and construction of geothermal resources, etc. Tangshan Baofeng Pipe Pile Co., Ltd. was jointly invested and established in November 2009 by Tianjin Baofeng Concrete Pile Co., Ltd. and Hong Kong Baofeng International Investment Co., Ltd.
Is there a guarantee for ground-mounted photovoltaic power plants on stilts?
Agricultural photovoltaic supplementation, photovoltaic supplementation for fishing and installation on a flat roof require all pile foundations. The standard module is a cement block of 40*40*40 cm (some pile foundations need to be increased according to the height of the support, wind pressure, snow pressure and other data).
The support for the installation of the photovoltaic energy production system is fixed on the pile foundation of! The pile foundation must support the weight of the inphotovoltaic installation itself, wind pressure, snow pressure and some natural disasters, etc. ! Everything must be calculated by competent technical personnel!
Do the embedded parts of cast-in-place photovoltaic piles need to be welded?
Yes. According to a query from news network CCTV, if the guarantee period for photovoltaic power generation is imposed by the state, it will be based on national quality and technical standards. The three-warranty period for photovoltaic power generation modules is five years, because photovoltaic power generation project manufacturers produce semi-finished products. The full warranty of components is 10 years, the warranty of power generation is 25 years, the full warranty of inverter is 5 years, which can be extended to 25 years, and the warranty of other materials should be 25 years old.
Yes.
According to the “Construction Method of Casting Plants for Photovoltaic Power Plants”, we learned that the processing method of the embedded parts of cast-in-place photovoltaic piles must be welded to achieve a good result. stabilizing effect. The embedded parts of the cast-in-place photovoltaic piles must therefore be welded.
The special function of cast-in-place photovoltaic piles is corrosion resistance, which makes the installation of piles more scientific and precise, making the construction of photovoltaic power plants more convenient and faster.