The method is as follows:
The location of the mountain peak was also determined by micro-site selection (a research process meticulous work and on-site research). The construction, transportation and installation of wind turbine sites on mountain tops are much more complicated than those on flat terrain.
After determining the location of the machine, the civil engineering staff must design the transportation route. Since each component of the wind turbine equipment weighs forty or fifty tons or even more, there are requirements for road width. slope and hardness of the road surface. Responsible for rollover accidents. According to the defined roads, build the roads first. Once the road construction machine is positioned, the aerial platform must be leveled and the foundation pit dug.
Once the foundations are completeborn, the tower, blades, hubs, generators and other components are arranged around the lifting platform, using a main crane with a capacity of 600 tons and 1 to 2 auxiliary cranes of 'a capacity of 600 tonnes. approximately 100 tonnes Install the tower section by section on the foundation, with flanged connections in the middle.
Under normal circumstances, a fan can be installed in one day.
After installation, the power should be transferred to the rear and the wind turbine should be debugged. Once everything is normal, it will be ready to produce electricity.