Qingjiangdong 5th Road, Weibin District, Baoji City, Shaanxi Province. According to the query map, the location of Baoji Wind Power Windmill is located on Qingjiang East 5th Road, Weibin District, Baoji City, Shaanxi Province. A high mountain wind tourism zone has been developed in this region. Along the Qinling Mountains, 99 large windmills wind and turn in a circle, the scenery is spectacular and majestic, no inferior to that of Mount Tai in Du Fu's View of the Mountains. where the stratus grows into the chest and the birds return from the canthus.
On May 20, the 48 MW Weihuidong Shuanma wind farm in Xinxiang, Henan, built by Hebei Engineering Company, was connected to the grid.
Henan Xinxiang Weihui East Shuanma Wind Farm Project is located in Weihui Town, Xinxiang, Henan Province, bordering the northern part of the Yellow River to the south and Taihang to the west. The total capacityThe installed capacity of the project is 48 MW, with a new 110 kV booster station and a supporting 110 kV transmission line. Hebei Engineering Company undertakes construction projects such as civil road construction in wind farms, construction and installation projects of wind generators and box transformers, as well as construction and installation of 35-meter collector lines. kV.
Since the start of the project on May 1, 2017, the project department has scientifically organized and carefully deployed, taking the construction technical specifications and measures as the starting point, and implemented safety and environmental measures. protection at all levels. We deployed personnel and machines rationally and made every effort to complete various tasks, overcoming the impact of protecting the ancient ruins of the Great Wall, successfully completingsuccessfully completed the construction tasks and successfully completed the owner's node plan.
The pouring of the wind turbine foundations was completed on October 31, 2018, the construction of the electricity collection line was completed on December 31, 2018 and the lifting of the wind turbine The turbine was completed on January 26, 2019. On May 14, 2019, production acceptance was adopted. On May 19, 2019, both collector lines and all box-type transformers were successfully connected to the grid and the first unit was connected. to the network for the production of electricity. The employees continued their efforts and realized that all units were connected to the grid for electricity generation on May 20. The objective.