The total investment is approximately RMB 7 billion and the total installed capacity is approximately 1,000 MW
The Abaga Banner project is expected to have an installed capacity of approximately 500 MW and is equipped with a 75 MW/150 MWh system. energy storage project. The project is expected to generate approximately 1,254.87 billion kilowatt hours of electricity per year. About 10 MW of wind power from the Abaga Banner project will be used for hydrogen production, and the hydrogen production volume is expected to reach 7.3 million standard cubic meters per year.
Jingneng Clean Energy said that as a development direction of new energy, hydrogen energy is in line with the company's development strategy and will help maintain the company's competition in the process of achieving carbon peaking and carbon advantage.
The Sunit Zuoqi project is expected to have an installed capacity of approximately 500 MW and is equipped with ae energy storage of 75 MW/150 MWh. The project is expected to produce approximately 1.528 billion kilowatt hours of electricity per year.
Jingneng Clean Energy said that once completed, these projects, together with nearby energy storage and thermal power plants, will increase wind and photovoltaic power generation capacities of the company, will reduce the waste of wind and photovoltaic energy. resources and realize wind power, integrated operation of photovoltaic power generation, energy storage and hydrogen production.