Binhai, Yancheng, Jiangsu, is a wind power generator. According to relevant public information, once the Binhai South H3 project is completed and put into operation, it will form Asia's largest offshore wind power cluster with the 100MW Binhai North H1 and 400MW Binhai North H2 offshore wind farms. MW which have been completed and operated. , with an annual power generation capacity of 2 billion kWh, compared with traditional coal-fired power plants, it can save 660,000 tons of standard coal and reduce carbon dioxide emissions by 1.58 million tonnes per year. Wind energy is a kind of clean energy. Compared with traditional fossil energy, it does not produce a large amount of carbon dioxide, sulfur dioxide and other pollutants. Therefore, it has little environmental pollution and has the advantages of environmental protection and energy saving. Binhai, Yancheng, Jiangsu province uses wind energy for electricity generation. The Binhai South H3 offshore wind power project is located in the Yellow Sea, 36 kilometers offshore. It is planned to deploy 75 wind turbines with a single capacity of 4 MW, with a total installed capacity of 300 MW. Since construction began in late 2019, State Power Investment Corporation Jiangsu Offshore Wind Power Co., Ltd. overcame difficulties such as long hours of offshore operations and insufficient manpower, and made every effort to accelerate the construction of the project, striving for success. complete and commission the project by the end of November 2023.
The process of converting installed wind energy capacity into power generation capacity is as follows:
Electricity production capacity = installed wind energy capacity × wind turbine operating hours
Example: < /p>
Awind power plant with an installed capacity of 200 MW has a total working hours of 2,000 hours per year, its electricity production capacity is therefore: 200 MW*2,000=400,000 MW. That is to say, the wind power plant can produce 400 million kWh of electricity per year.