The test pressure is 1.5 times the working pressure of the pipeline system, but should not be less than 6 kg.
1. Block each water distribution point in the pressure test pipe section, slowly inject water and at the same time exhaust the air in the pipe.
2. Once the pipe is filled with water, carry out a leak check.
3. After pressurizing the system, the pressure should be increased slowly using a hand pump and the pressure increase time should not be less than 10 minutes.
4. After the pressure is increased to the specified test pressure, stop pressurizing, stabilize the pressure for 1 hour, and observe whether there is leakage at each interface.