The 20 MW photovoltaic plant is a large-scale project.
The project covers an area of approximately 50 hectares and costs 200 million. It's a big project.
Photovoltaic power plant refers to a photovoltaic power generation system connected to the power grid and transmitting energy to the power grid. This is a state-sponsored green energy project. It can be divided into grid-connected power generation systems with and without batteries. Solar power generation is divided into photothermal power generation and photovoltaic power generation. Solar power generation generally refers to the production of solar photovoltaic power.
20 MW
Photovoltaic power plant construction plan
The total construction period is only three months. Preparation (site preparation, material preparation, temporary construction installations) prend of time. , and subsequent steps A few days are reserved for curing the concrete, but the actual curing time is only more than two months. In order to ensure the construction period, the number of people will be increased or decreased flexibly according to the specific workload and project progress.
Project construction arranges flow operations according to the number of square arrays, starting from the top square array ① in horizontal rows down, to the last square array ⑥, substation . The building can be built together. with the foundation, and the complete building and distribution room can be constructed separately during the foundation construction period. Special construction technology: It is recommended to use cast-in-place cylindrical piles as the foundation of the component support and integrate 8 thick 150X150 Q235 steel plates as the welding surface of the supportand the foundation. This can eliminate the occurrence of this phenomenon. construction of supports and foundations in a wide range of errors.
In terms of construction machinery and equipment: consider installing 2-4 small mobile mixers on site, and working in shifts can ensure material supply needs. Provide 2 small motorized dump trucks and 3 trolleys for each mixer to transport the concrete. If the project requires it, a concrete delivery pump may be considered to meet concrete delivery requirements in complex terrain.