Relevant data on diesel generator room design
Unit power (kW) Standard machine room (length, width and height mm) Exhaust shaft and outlet area with fan (㎡) Air inlet area ㎡ (with fan) Air inlet Area ㎡ (natural air intake) Fan exhaust flow rate (m?/min) Unit size (length, width and height mm) Weight (kg) Area between fuel tanks (㎡)
220 7000×4000×4500 1.6 2.0 4.0 490 3000×980×1530 3100 2
275 7200×4000×4500 1.7 2.1 4.2 490 3150×980×1530 3250 2
310 7200×4000×4500 1.7 2. 1 4.2 490 3150×980×1530 3400 3
330 7300×4250×4500 2.3 3.0 6.0 490 3300×1250×1800 3600 3
360 7300×4380×4500 2.6 3.2 6.4 4 90 3300× 1380×1550 3700 3
400 7550×4250×4500 2.6 3.2 6.4 588 3550×1250×1800 4350 3
440 7750×4250×4500 3.0 3.5 7.0 588 3 750×1250× 1800 4800 4
500 7750×4920×4500 3.0 4.5 9.0 735 3750×1920×2300 5000 4
550 7750×4920×4500 3.2 4.5 9.0 735 3750×1 920×2300 5400 4
660 8650×4650×5000 4.0 6.0 12.0 900 4650×1630×2320 92504
704 8650×4650×5000 4.0 6.0 12.0 900 4650×1630×2320 9350 5
1. Regarding the minimum clearance size required by the manufacturer of the smoke exhaust pipe well (mandatory): one 800x800mm for generator; 1200x1200mm for two generators. Increase appropriately when conditions permit.
2. Regarding the clearance size of the spray dust removal room (suitable to be installed): 1800x2000mm when one generator is used; 1800x2800mm when two generators are used together.
(For reference only: Fujian Yanan Motor Answer)
1. First-level technical maintenance of 800kw diesel generator: (50-80 hours) Add to the content of daily maintenance< /p>
1. Clean the air filter and replace it if necessary;
2. Replace the diesel filter, air filter, and water filter;
3. Check the tension of the drive belt;
4. Add lubricating oil to all oil nozzles and lubricating parts;
5. Replace the cooling water
II. 800kw Second-level technical maintenance of diesel generator: (250-300 hours) added to the content of daily maintenance and first-level maintenance
1. Clean the piston, piston pin, cylinder liner, piston ring, connecting rod bearing and Check its wear and tear;
2. Check whether the inner and outer rings of the rolling main bearing are loose;
3. Remove scale and sediment in the water channels of the cooling water system;
4. Clear the carbon deposits in the cylinder combustion chamber and intake and exhaust passages;
5. Check the valves, valve seats, push rods and rocker arms for wear and tear, and perform grinding adjustments;
p>
6. Clean the carbon deposits on the turbocharger rotor, check the wear of the bearings and impellers, and replace them if necessary;
7. Check whether the bolts of the coupling between the generator and the diesel engine are loose. Sliding teeth should be repaired if problems are found.
3. Three-level technical maintenance of 800kw diesel generator: (500-1000 hours) added to the contents of daily maintenance, first-level maintenance and second-level maintenance
1. Inspection and adjustment Lift the fuel injection angle;
2. Clean the fuel tank;
3. Clean the oil pan;
4. Check the atomization of the fuel injection nozzle
p>
Users must pay attention to the care and maintenance of the unit when using the 800kw diesel generator at different stages to reduce unit failures and extend the service life of the unit.