February 2022. According to information released on the official website of China Resources Group, the total construction period of the wind power plan is 12 months. The project has started in July 2022 and is planned to be connected to the grid in July 2023. The project's annual power generation is 57.9 million kilowatt-hours, and compared with coal-fired power plants, it can save 18,500 tons of standard coal every year.
When will China Resources Jianshi Wind Power Plant start construction?
Introduction When will China Resources Construction Wind Power Plant start construction in February 2022? According to information released on the official website of China Resources Group, the total construction period of the wind power plan is 12 months, and the pro