On May 20, the 48-MW wind farm Weihuidong Shuanma in Xinxiang, Henan, built by Hebei Engineering Company, was connected to the grid.
Henan Xinxiang Weihui East Shuanma Wind Farm Project is located in Weihui City, Xinxiang, Henan Province, bordering the northern part of the Yellow River to the south and Taihang to the west. The total installed capacity of the project is 48 MW, with a new 110 kV booster station and a supporting 110 kV transmission line. Hebei Engineering Company undertakes construction projects such as road civil construction in wind farms, construction and installation projects of wind power generators and box transformers, and construction and installation of 35 kV collector lines.
Since the project started on May 1, 2017, the project department has scientifically organized and carefully deployed, taking construction technical specifications and measures as the starting point, and implemented safety and environmental protection at all levels. Stick to quality. We rationally deployed personnel and machinery and went all out to complete various tasks, overcoming the impact of the protection of the ancient Great Wall ruins, successfully completing the construction tasks, and successfully realizing the owner's node plan.
The foundation pouring of the wind turbine was completed on October 31, 2018, the construction of the power collection line was completed on December 31, 2018, and the hoisting of the wind turbine was completed on January 26, 2019. On May 14, 2019, the production acceptance was passed. On May 19, 2019, the two collector lines and all the box-type transformers were successfully connected to the grid and the first unit was connected to the grid for power generation. The employees continued their efforts and realized all units were connected to the grid for power generation on May 20. goal.