Fengtan Hydroelectric Power Station was designed in 1969 by the Design Institute of the Ministry of Water Resources and Electric Power (formerly the Water and Water Resources Study and Design Institute). of Changsha Electric Power) and the engineering of the Fengtan hydroelectric power station of Hunan province. The headquarters organized the construction of the main project.
The project started on October 1, 1970 and the first unit was commissioned on May 1, 1978. In November 1979, all four units were completed and commissioned.
It was built by the construction engineering headquarters of Fengtan Hydropower Station of Hunan Province in 1970. The first unit was put into operation for power generation in May 1978, and all four units were commissioned in 1979.