?82 units.
At present, all access roads to the project have been connected, and 8 of the 82 wind turbine units planned to be constructed have now been completed. The project plans to complete the connection of the first batch of wind turbines to the grid on April 15.
It is understood that the start of construction of the CNNC Suining Wind Power Project is an effective practice for our county to use advantageous wind resources to promote sustainable development. The project was launched in July last year with a total investment of 1.8 billion yuan. It is mainly located in Weiji, Liangji and Suihe streets, with a total scale of 230 megawatts. Among them, the total investment of the Weiji Town project is 1.368134 million yuan, with a scale of 180 megawatts.
Bao Wei said: “Taking the Huaiyuan project at Lakeside as an example, after calculation, the total annual power generation after grid-connected power generation is 202 million kilowatt hours, which can reduce ash emissions by about 20,000 tons. ”