Preparation, charging preparation, charging process, testing and evaluation.
1. Before conducting the full test, the energy storage equipment needs to be inspected and prepared to ensure the normal operation, safety and reliability of the equipment.
2. Connect the wind power generation system to the energy storage equipment, ensure that the connection lines are correct, and start the wind power generation system to start generating electricity.
3. When the battery of the energy storage device reaches a fully charged state, the full test is completed. At this time, the power generation of the wind power generation system is stopped and the charging connection is disconnected.
4. After the full test is completed, test and evaluate the energy storage equipment, record the relevant data during the full test, and analyze it.