Photovoltaic power generation project. The National Energy Administration issued the "Notice on Matters Concerning the Development and Construction of Wind Power and Photovoltaic Power Generation in 2021". As of September 13, 2022, photovoltaic power generation projects will be adopted. Photovoltaic power generation refers to the process of converting solar energy into electrical energy through photovoltaic power generation systems. Compared with wind power projects, photovoltaic projects adopt a filing system. The local competent authorities have different regulations on the supporting documents that should be obtained before filing, which are usually more simplified.
Competition for new energy wind power development may encounter the following problems:
1. Dispute over scoring rules: On June 18, 2020, a city announced The "Announcement on Preferred Competitive Allocation of Wind Power Projects" was issued. In accordance with the requirements of the "Liaoning Province Wind Power Project Construction Plan" (Liao Fagai Energy [2020] No. 253), the city can add 600,000 kilowatts of wind power into production before 2025. Promote the sustainable and healthy development of renewable energy. However, the wind power competitive allocation method in a certain city has caused confusion among colleagues in the wind power circle. The wind power competitive allocation method downplays the factor of low-price competition in the rule setting.
2. Project construction cycle issues: Xinjiang Construction Corps released "Xinjiang Production and Construction Corps 2021 Wind Power and Photovoltaic Power Generation Project Competitive Configuration 6 Bid Sections: 40,000-kilowatt photovoltaic for the 130th Regiment of Huyanghe City, the Seventh Division of the Corps Announcement of Tendering and Invitation for Investment Entities in Power Generation Projects (Second). Announcement requirements: Full capacity grid connection conditions must be met by the end of December 2022. On the premise of ensuring project safety, quality and ecological environmental protection, bidders are encouraged to shorten the project construction cycle by optimizing the project construction plan.
3. Project construction progress issues: In principle, the supporting energy storage scale will be constructed simultaneously with the project itself. The winning bidder should strictly abide by the project construction progress requirements and complete the project construction work on time. If the project is not completed and connected to the grid after the deadline, it will no longer be included in the scope of the guaranteed grid connection project. The project can fairly participate in the market-based grid connection project application, but will not enjoy priority grid connection. Conditions (except for force majeure during the development period).