The method is as follows:
The location of the mountain top was also determined through micro-site selection (a meticulous research process and on-site research work). The construction, transportation and installation of wind turbine positions on mountaintops are much more complicated than those on flat terrain.
After determining the location of the machine, civil engineering personnel need to design the transportation road. Since each component of the wind turbine equipment weighs forty or fifty tons, or even heavier, there are requirements for road width, slope, and road surface hardness. Responsible for rollover accidents. According to the set roads, build the roads first. After the road construction machine is positioned, the lifting platform must be leveled and the foundation pit dug.
After the foundation is completed, arrange the tower, blades, hubs, generators and other components around the lifting platform, using a main crane with a capacity of 600 tons and 1-2 auxiliary cranes with a capacity of about 100 tons. Install the tower section by section on the foundation, with flange connections in the middle.
Under normal circumstances, one fan can be installed in one day.
After installation, the power needs to be reversed and the wind turbine debugged. Once everything is normal, it will be ready to generate electricity.