Ten thousand and fourteen. Two wind power generators can be built on one acre of land, and 14,000 wind turbines need to be installed on 7,000 acres of land. The spacing of large wind turbines is generally 10-15 times the diameter of the wind wheel, which is a spacing of 700 to 1,000 meters. Wind turbines are electrical equipment that convert wind energy into mechanical work, which drives the rotor to rotate and ultimately outputs alternating current.
1. Foundation construction, the main work is the foundation civil construction of wind turbines, and may also include the construction of booster stations. Construction engineering qualifications are required, and general construction companies can do it
2 .Wind turbine crane installation work mainly includes wind turbine hoisting and electrical installation. It requires power equipment installation qualifications and at least 400T crane installation qualifications. Generally, provincial and municipal power construction companies have this qualification
3. Collection line laying , mainly including the laying or erection of on-site lines, which requires power equipment installation qualifications, which many construction units have
4. Wind turbine debugging requires on-site personnel from the equipment manufacturer to debug
5. Main transformer Debugging requires debugging by the equipment manufacturer
Generally, this is all, there may be some additional work such as SVC installation and debugging, communication line debugging, etc., which requires a corresponding construction team