Legal analysis: After wind power is completed, the land reclamation obligor will carry out reclamation according to the land reclamation plan submitted in the previous stage. After the reclamation task is completed, an application for acceptance shall be made to the land and resources department of the local people's government at or above the county level in accordance with the regulations of the land and resources department of the State Council. The land and resources department that receives the application shall work with the agriculture, forestry, environmental protection and other relevant departments at the same level. After inspection and acceptance, if the land reclamation obligor passes the inspection, a certificate of acceptance will be issued to the land reclamation obligor.
Legal basis: Article 3 of the "Land Reclamation Regulations" Land damaged by production and construction activities shall be reclaimed by the production and construction units or individuals (hereinafter referred to as land reclamation) in accordance with the principle of "whoever damages it shall reclaim it" Obligor) is responsible for reclamation. However, for land that has been damaged by the production and construction activities of the land reclamation obligor due to historical reasons (hereinafter referred to as the damaged land left over from history), the people's government at or above the county level is responsible for organizing the reclamation. People's governments at or above the county level are responsible for organizing the reclamation of land damaged by natural disasters.
Article 11 of the "Land Reclamation Regulations" states that the land reclamation obligor shall prepare a land reclamation plan in accordance with the land reclamation standards and the regulations of the land and resources department of the State Council.
Article 13 of the "Land Reclamation Regulations" states that the land reclamation obligor shall submit a land reclamation plan along with the relevant approval materials when applying for construction land or mining rights.
Article 28 of the "Land Reclamation Regulations" After completing the land reclamation tasks in accordance with the requirements of the land reclamation plan, the land reclamation obligor shall report to the local county level in accordance with the provisions of the land and resources department of the State Council. When the land and resources administrative departments of the above local people's governments apply for acceptance, the land and resources administrative departments that receive the application shall conduct the acceptance inspection together with the relevant departments of agriculture, forestry, environmental protection, etc. at the same level. For land reclamation acceptance, relevant experts should be invited to conduct on-site inspections to check whether the reclaimed land meets the land reclamation standards and the requirements of the land reclamation plan, verify the type, area and quality of the reclaimed land, and Announce the preliminary acceptance results and listen to the opinions of relevant rights holders. If the relevant rights holder raises objections to the completion of land reclamation, the land and resources department shall further verify the situation in conjunction with the relevant departments and provide feedback on the verification to the relevant rights holder; if the situation is true, rectification opinions shall be provided to the land reclamation obligor.
Article 29 of the "Land Reclamation Regulations" The land and resources department responsible for organizing the acceptance inspection shall, together with the relevant departments, complete the inspection and acceptance within 60 working days from the date of receipt of the land reclamation acceptance application. If the land reclamation obligor passes the inspection and acceptance, a confirmation of acceptance will be issued to the land reclamation obligor; if the land reclamation obligor fails to pass the inspection and acceptance, a written rectification opinion will be issued to the land reclamation obligor, stating the matters that need to be rectified. Apply for acceptance.
Article 30 of the "Land Reclamation Regulations" After the completion of a government-invested land reclamation project, the land and resources department responsible for organizing the implementation of the land reclamation project shall comply with Article 28 of these Regulations. Conduct preliminary acceptance according to the provisions of the payment. After preliminary acceptance is completed, negativeThe land and resources department responsible for organizing the implementation of land reclamation projects shall apply to the land and resources department of the people's government at the higher level for final acceptance in accordance with the provisions of the land and resources department of the State Council. The land and resources department of the people's government at the higher level shall organize timely acceptance inspection together with relevant departments. After the completion of a land reclamation project that is carried out by the land rights owner on its own or with social investment, the land and resources department responsible for organizing the implementation of the land reclamation project shall conduct acceptance inspection together with relevant departments.
Article 31 of the "Land Reclamation Regulations" If the land is reclaimed for agricultural use, the land and resources department responsible for organizing the acceptance inspection shall, together with the relevant departments, conduct an inspection on the effects of land reclamation within 5 years after passing the inspection and acceptance. Follow up and evaluate, and propose suggestions and measures to improve land quality.
Yes
There is no separate certificate for wind power construction license; if there is a wind power project, it includes During the construction preparation of wind power projects, construction transportation, basic engineering construction, wind power equipment installation, wind farm debugging and trial operation, construction safety and environmental protection, and project acceptance, corresponding documents should be obtained during each period of wind power project construction. Construction license; each process also has relevant technical standards; and each project process will be handed over to a company with relevant qualifications according to the construction standards; because the standards are different, the qualification certification requirements are also different, and some qualifications are different Companies cannot be certified at the same time; however, the qualification certification departments for such projects are the Ministry of Housing and Urban-Rural Development of each region.