The necessary procedures and processes are as follows:
First of all, once the hydroelectric plant is built and has the necessary conditions for electricity production, contact the company local electricity supply and the national ministry of development and reform. Commission. After acceptance, you can go online to generate electricity. But it's more difficult.
The first difficulty is that there is no state subsidy for water and electricity. The National Development and Reform Commission has a high threshold. Although the State Grid Corporation of China has stated that in projects built on user-owned hydropower sources, all the energy produced can be brought online, all the energy is self-used, or the remaining energy can be put online at the user's choice. will be supplied by the electricity network, and the prices ofThe purchase and sale of the electricity generated will be implemented. To benefit from subsidized electricity prices, private electricity generation must obtain approval from the local Development and Reform Commission. To submit a project application to the National Development and Reform Commission, you must also submit a project report prepared by an engineering consulting agency with Class A qualifications.
The second difficulty is that it looks free, but actually you have to pay a project fee. Although the State Grid Corporation of China has stated that as long as the scale of the power generation project does not exceed 6 megawatts and the voltage level is 10 kV or less, it can be connected to the grid, the State Grid Corporation will not charge any fees. charges for the entire process of connecting to the network. But this is only the technical consultation, the acceptance of the projetting, debugging, etc. required for the power supply to be connected to the power grid. In the entire private power generation project, the largest investment in equipment and power supply must be borne by the user. .