Project approval
1. The city (county) government will approve the project based on the feasibility study report; 4. The city and county science and technology offices are required to coordinate with relevant departments to provide; corresponding information (electronic documents and electronic drawings are provided) (1) Certification documents for solar energy resources and climatic conditions of the project construction site. Detailed meteorological and hydrological data for the last 10 years provided by the local meteorological office, mainly including: monthly radiation throughout the year, average monthly sunshine duration, sunrise (sunset) time, minimum (high) temperature and average precipitation can provide weather data such as rain, snow, wind speed and depth of frozen ground.(2) Geographic conditions of the project construction site: the name, geographic location, longitude, latitude, and altitude of the project construction site. (3) Site overview and drawings (the project construction site is an open space) The project construction site is an open space, and a site overview and drawings shall be provided, mainly including the site area, the geology, topography and surrounding environment. (4) Local power grid situation and grid connection conditions 1) The specific situation of the local power grid, mainly including the current electricity price, average daily electricity consumption, number and capacity of transformers and the distance to the project construction site, as determined by the network distribution situation provided by the local electricity supply company and the company's supportlocal electricity supply for connection to the network; 2) The total electrical load of all electricity around the photovoltaic power generation project site (should be slightly larger) than the total installed photovoltaic power generation capacity 2 MW), the general layout plan surroundings of the electrical substation and distribution room, general electrical description, 10 kV power system diagram, 0.4 kV power system diagram, floor plan of the distribution room distribution, electrical distribution power and distribution diagram of the room, lightning protection, grounding board of all units, quantity, microgrid projects must also provide the power consumption of the load, load characteristics and power supply time 3) Transmission and distribution lines around photovoltaic power generatione ; project site: the location and distance of 10KV, 110KV and 220KV photovoltaic power plant; < /p>
1. Dial 95598 to apply
2. Power Generation Project Grid Connection Application Form" and "Project System Design and Implementation Plan", and the national grid will be officially accepted. After acceptance, the local power supply office will conduct an on-site inspection of the project location
3 Formulate an access plan State Grid will publish a project grid connection plan based on the owner's project conditions. >
4 Confirm the connection system plan The owner requesting a network connection reviews and confirms the access system plan.
5 Issues a letter of opinion on the connection to the network. network.
The owner who requests a connection to the network receives a letter of opinion on the connection to the network issued by the electricity network.that
6. Project approval and technical construction
The owner completes the project construction works such as installation of photovoltaic panels
7. Submits an application for acceptance and commissioning of the grid connection
The owner completes the “Request Form for Acceptance and Commissioning of Distributed Photovoltaic Power Generation Projects”
p>
8. and commissioning
State Grid will come to inspect and accept the owner's project, replace the meter and sign an order with the owner Electricity Agreement
To be honest, as long as the owner of your roof is clear and the electric meter is independent, everything will be fine. It's easy to apply. Of course, you need a housing certificate when applying. If you live in an urban area, you also need to consider certain requirements from the city building department, etc. He is giftIt's best to find a photovoltaic company to do it. On the one hand, you know her, and on the other hand, you have good connections, so you will be able to find the person responsible more easily.